Saltwater disposal facility dirt work and construction

Alpha Wolf Excavation & Construction was selected to build this SWD facility in Howard County, TX. Facility was designed to handle 20,000 BPD injection capacity with 5,500 BBL tank storage including 1,200 BBL oil storage across 5 acre lease site. Project involved approximately 2,000 man-hours over a 60-day project duration.