Scope of Work
Furnished equipment and operations for seven (7) Wellsite Facilities, each including:
- (2) Skid Mounted 65 ton Mechanical Refrigeration Units with NGL Stabilizer Towers
- (2) 18,000 gallon NGL Bullet Tanks with unloading bulkheads
Overview
Due to the pre-packaged, single skid design, Torrent was able to install and commission equipment on each of the seven (7) existing facilities in three weeks after kick-off. The equipment operated reliably and met all required gas conditioning and NGL specifications.
Equipment included
- ASME Code Equipment
- PLC Controlled Automated Process
- Design Basis for Broad Operating Ranges
- Robust Equipment for Improved Run-time
Contract Type
Rental contract including equipment and operations
Listing created