Remove and replace an existing weld in 26" 600# gate valve in an existing compressor station. Isolate and blow down piping via 1-30" and 2-26" 600# stopples. Isolate, blowdown, and replace valve setting with new valve and goal post blow down assembly all while station was in service. Install all new stopple fittings, anchor block, and TOR's in house.
Keywords:
Stopple, valve, in service, tie ins, block valve