Pipeline Construction: 11,000LF of 20" SDR 11

Lay and tie in 11,500LF of 20" SDR 11, and 850LF of 12" SDR 7. Project included hot tie ins to existing pipelines at three different locations, lateral tie ins, steel fabrication/installation/painting of gas/water meter headers, risers, and block valves settings. All work completed safely and on schedule.

Keywords: Pipeline construction, tie ins, welding, fabrication, ditching, fusion, HDPE, fusing